Program Management Professional (PgMP) — Free Practice Questions
10 free sample questions from a bank of 656, with the correct answers and explanations. No signup required — start practising right now.
1Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?
Change requests
Earned value management results
Stakeholder analysis plan
Performance reports
Answer: C
The short version
C — large-stakeholder distribution needs the stakeholder analysis plan. The settled key supplies needs and channels as the distribution input.
Key concepts in this question
Information distribution: delivering the right content to the right stakeholder at the right time.
Stakeholder analysis plan: maps influence, interest, information needs, and preferred modality.
Communications plan contrast: defines how and what is communicated, but analysis tailors it per stakeholder.
Performance-report contrast: an output of execution, not the input that shapes distribution.
Scale pressure: 121 stakeholders make generic broadcasting ineffective without segmentation.
Why C is correct
C is correct because the stakeholder analysis plan identifies who needs what information and through which channel, which the distribution process consumes to route messages. With 121 stakeholders, tailoring by influence and modality is essential. Vendor prose confirms analysis as the key input alongside the communications plan.
Why the others are wrong
A. change requests trigger updates but do not define stakeholder needs.
B. earned value results are status content, not distribution inputs.
D. performance reports are outputs sent out, not inputs that plan routing.
PgMP exam tip
Distribution input equals stakeholder analysis: who needs what and how.
2You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?
This is an example of a preventive action.
This is an example of team development.
This is an example of quality assurance.
This is an example of a corrective action.
Answer: A
The short version
A — training plus trial use before work is preventive action. The settled key classifies proactive avoidance of future defects.
Key concepts in this question
Preventive action: proactive step to eliminate causes of potential nonconformance before it occurs.
Training investment: upskilling users of untested materials to prevent delays and waste.
Pilot experimentation: purchasing sample materials for practice to surface issues early.
Corrective contrast: fixes actual nonconformance after it has entered the work.
Assurance and development contrast: process audits and team growth support quality but are broader than this preemption.
Why A is correct
A is correct because sending staff through training and funding practice runs occurs before project work to ensure mistakes never enter the effort. That forward-looking avoidance matches the PMI definition of preventive action. Vendor prose confirms proactive prevention rather than correction of existing defects.
Why the others are wrong
B. team development builds general competency, not the specific defect-prevention action.
C. quality assurance audits processes, while this scenario prevents a concrete material risk.
D. corrective action responds to realized problems, but no mistake has yet occurred.
PgMP exam tip
Before-work training plus practice equals preventive, after-defect fix equals corrective.
3A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
Reactionary risks
Chain risks
Secondary risks
In flux risks
Answer: C
The short version
C — risks created by a response are secondary risks. The settled key uses PMI risk-response terminology precisely.
Key concepts in this question
Risk response execution: applying avoidance, mitigation, transfer, or acceptance to a tracked risk.
Secondary risk definition: a new risk that exists only because the response was implemented.
Residual contrast: leftover exposure from the original risk after response, not a new risk.
Chain and reaction wording: informal labels with no PMI definition for this mechanism.
Response planning duty: secondary risks must be identified and added to the register.
Why C is correct
C is correct because PMI defines secondary risks as those arising directly as a result of implementing a risk response. If the response had not been taken, the secondary risk would not exist. The question scenario of a response causing new risks maps word-for-word to that definition.
Why the others are wrong
A. reactionary risks is not a PMI term for response-generated risks.
B. chain risks suggests linkage but lacks the formal response-cause meaning.
D. in flux risks is not a recognized risk category.
PgMP exam tip
Response creates new risk equals secondary, response leaves old risk equals residual.
4You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?
$750,000
$795,000
$750,001
$946,857
Answer: D
The short version
D — four-year six-percent growth on 750K needs at least 946857. The settled key applies compound future value to the program decision.
Key concepts in this question
Future value formula: FV equals PV times one plus rate raised to periods for compound growth.
Opportunity cost logic: management compares program return against safe six-percent compounding.
Four-year exponent: 1.06 to the fourth power captures annual reinvestment of gains.
Minimum threshold: the program must beat the risk-free accumulation to justify selection.
D is correct because 750000 times 1.06 to the fourth equals approximately 946857, the amount the same funds would become at six percent. Management therefore requires at least that value for the program to outperform the baseline. Vendor math confirms 946857 as the computed hurdle.
Why the others are wrong
A. 750000 ignores any time value and guarantees a real loss versus interest.
B. 795000 reflects roughly one year of simple growth, not four years compound.
C. 750001 adds a token dollar and still trails the required accumulation.
PgMP exam tip
For return hurdles compute PV times one-plus-rate to the power of years.
5You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?
Analogous estimating
Organizational process assets
Parametric scope definition
Template driven
Answer: A
The short version
A — Analogous estimating. Using the previous project's scope as the basis for the new one is the textbook use of historical information, and "template driven" is not a defined type of scope definition.
Key concepts in this question
Analogous estimating: Using values or attributes from a previous, similar project or activity as a basis for the current one.
Benchmarking: Comparing the current project to other projects to improve or reuse their practices.
Organizational process assets (OPAs): Policies, process procedures, templates and historical information the team draws on; an input, not a scope definition technique.
Parametric estimating: Uses a statistical model relating other variables to cost/duration/scope; not described here.
Why A is correct
Scope definition in PMBOK is supported by data analysis and benchmarking, i.e. using historical information and lessons learned from similar projects. Modelling this project's scope on the HHG Project you just ran is exactly analogous estimating/benchmarking. "Template driven" does not appear in PMBOK or the current Examination Content Outline as a type of scope definition, so it cannot be the keyed answer.
Why the others are wrong
B. Organizational process assets are an input category, not a "kind" of scope definition.
C. Parametric scope definition would require a mathematical model relating variables to scope, which is not described.
D. "Template driven" is not a recognized PMBOK scope definition method.
PMP exam tip
"Past similar project" always signals analogous estimating or benchmarking; if an option's label is not in the PMBOK glossary, treat it as a distractor.
6What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?
Run chart
Scatter diagram
Control chart
Pareto diagram
Answer: B
The short version
B — variable-to-variable correlation over time is a scatter diagram. The settled key distinguishes correlation charts from control tools.
Key concepts in this question
Scatter diagram use: plots paired observations to reveal positive, negative, or no correlation.
Time dimension: points collected over time still show how two variables move together.
Run chart contrast: tracks a single variable trend without comparing a second variable.
Control chart contrast: adds specification and control limits to judge process stability.
Pareto contrast: ranks defect categories by frequency to prioritize causes.
Why B is correct
B is correct because quality teaching defines the scatter diagram as the tool that compares two or more variables to determine how closely they may be related. Plotting one variable against another exposes clustering along a line or curve. That correlation purpose matches the question wording exactly.
Why the others are wrong
A. run chart shows one variable trend, not inter-variable relation.
C. control chart tests stability against limits, not correlation strength.
D. Pareto diagram prioritizes categories, it does not correlate variables.
PgMP exam tip
Two variables plus relationship equals scatter, one variable plus time equals run.
7All of the following are resources that need to be monitored and controlled except for which one?
Equipment
Staff
Quality
Facilities
Answer: C
The short version
C — settled key treats Quality as the non-resource exception. The explanation follows the flagged key for monitor-and-control scope.
Key concepts in this question
Resource monitoring: tracking availability and performance of people and physical means.
Equipment and staff: tangible capacity that is assigned, leveled, and controlled.
Facilities: physical locations that support work and are scheduled as resources.
Quality framing: in this syllabus Quality is presented as a requirement and metric set, not a monitored resource.
Monitor-and-control list: the tested set expects three resource items plus one exception.
Why C is correct
C is correct under the settled key because Quality is classified as the item that is planned and assured rather than monitored and controlled as a resource. Equipment, staff, and facilities are treated as the resource pool requiring ongoing monitoring. The explanation therefore credits Quality as the except choice per the flagged answer.
Why the others are wrong
A. under this settled key, Equipment is treated as a monitored resource.
B. under this settled key, Staff is treated as a monitored resource.
D. under this settled key, Facilities is treated as a monitored resource.
PgMP exam tip
For this bank row memorize C as settled exception: Quality out, rest monitored.
8What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
pert
gert
pmis
Monte Carlo
Answer: D
The short version
D — optimistic to pessimistic combinations mean Monte Carlo simulation. The settled key selects probabilistic schedule modeling.
Key concepts in this question
Three-point estimates: optimistic, most likely, and pessimistic durations for each activity.
Monte Carlo method: thousands of random draws from those distributions to build outcome probabilities.
PERT contrast: uses weighted average for a single expected value, not full combination sampling.
GERT contrast: graphical evaluation of network logic branches, not the credited simulation here.
PMIS contrast: the information system hosting data, not the analysis technique.
Why D is correct
D is correct because Monte Carlo simulation explicitly combines optimistic, most likely, and pessimistic outcomes across activities to show possible schedule distributions. Project managers use its cumulative curves to set confidence dates. The scenario wording of possible combinations matches Monte Carlo teaching.
Why the others are wrong
A. pert computes expected duration, not sampled combinations.
B. gert models conditional branching, not mass schedule sampling.
C. pmis stores and reports data but performs no simulation.
PgMP exam tip
Combinations of three estimates through sampling equals Monte Carlo.
9All of the following are resources that you will need to monitor and control in a program environment except for which one?
Staff members
Contracts
Quality
Equipment
Answer: C
The short version
C — Quality. Staff members, contracted sellers and equipment are resources you monitor and control; quality is a management dimension, not a resource.
Key concepts in this question
Program resources: People (staff, contractors), equipment, facilities, materials, supplies and budget — the things assigned and controlled.
Contracts / procurement: Managed and controlled for outsourced (contracted) resources — sellers are resources.
Quality: An attribute of program work monitored through program quality management; never listed as a resource.
Why C is correct
The question asks which item is not a resource you monitor and control. Staff members, resources obtained through contracts, and equipment are all program resources under resource management. Quality is not something you assign or schedule — it is a characteristic of the deliverables and work, managed through quality planning, assurance and control, so it cannot be grouped with the resource items.
Why the others are wrong
A. Staff members are program resources and are monitored/controlled for utilization and performance.
B. Contracts deliver contracted resources (sellers) whose work must be monitored and controlled.
D. Equipment is a classic program resource requiring tracking, assignment and control.
PMP exam tip
Resources = people, equipment, facilities, materials, supplies, budget. Quality never appears on a resource list.
10What cost estimating approach uses the work breakdown structure to create a cost estimate?
Analogous
Definitive
Top down
Parametric
Answer: B
The short version
B — WBS-driven costing is definitive estimating. The settled key links bottom-up detail to the most accurate estimate class.
Key concepts in this question
Work breakdown structure: decomposition of total scope into work packages for ownership and measurement.
Definitive estimate: detailed bottom-up rollup used for budgets and baselines.
Analogous contrast: top-down comparison to prior projects without WBS detail.
Parametric contrast: statistical rate-times-quantity models rather than package rollups.
Accuracy progression: definitive follows preliminary ranges once scope is fully defined.
Why B is correct
B is correct because building costs from individual WBS work packages upward is the textbook definition of definitive, also called bottom-up, estimating. It aggregates labor, materials, and contingency at the lowest level for maximum accuracy. Vendor prose confirms the WBS-to-definitive linkage.
Why the others are wrong
A. analogous uses history, not WBS decomposition.
C. top down allocates gross totals without package detail.
D. parametric applies unit rates, not a WBS rollup.
PgMP exam tip
WBS plus rollup cost equals definitive bottom-up estimate.