Project Management Professional (PMP) — Free Practice Questions
10 free sample questions from a bank of 1611, with the correct answers and explanations. No signup required — start practising right now.
1A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
Consult the risk register for an appropriate planned risk response and implement.
Revise the project management plan and move the task to a time when the technical resource will be available.
Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
Update the lessons learned report and the risk log to reflect that this risk has materialized.
Answer: A
The short version
A — Implement the planned response held in the risk register. The risk was identified during planning, so a response, owner and trigger already exist and must now be carried out.
Key concepts in this question
Identified risk vs. issue: An identified risk has a recorded response. Once its trigger occurs it becomes an issue, and the response already written for it is what gets executed.
Risk register: The output of Plan Risk Management that captures each identified risk, its triggers, its planned response and its owner.
Response strategies: Threat responses are avoid, mitigate, transfer, accept or escalate; a pre-agreed mitigation here means activating reserves, cross-training or an alternative resource.
Change control: Anything that alters the schedule, scope or budget baseline requires a change request rather than a unilateral plan edit.
Why A is correct
The scenario deliberately states the risk was identified during planning, so the project holds a documented, approved response for exactly this event. The engineer's leave is the trigger firing, and implementing the pre-planned response is the fastest, least-disruptive path to protecting the critical path, exactly as PMI expects a project manager to do under due diligence. Record and execute first; re-plan only what the response cannot cover.
Why the others are wrong
B. Rescheduling the task edits the schedule baseline on the project manager's own authority without a change request, and ignores the response already agreed.
C. Removing scope to fit a resource gap deletes an approved business requirement unilaterally, trading a delivery goal away.
D. Updating logs and lessons learned is record-keeping only; documentation does not mitigate any schedule impact.
PMP exam tip
Risk already in the register and now occurring? Execute the planned response — never improvise a re-plan or a scope cut.
2A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
Ask the team member to learn the new system as on-the-job training.
Issue a change request to extend the project schedule.
Escalate the team member's performance to the project sponsor.
Assign an experienced resource to support the team member.
Answer: D
The short version
D — Assign an experienced resource to support the team member.
Key concepts in this question
Capability gap vs. performance: a trainable skill gap is addressed by support and knowledge transfer, not by escalation or replacement.
On-the-job training: useful but slow; it works when the deadline pressure is low.
Escalation: a last resort for persistent performance problems, not for a new system the member simply has not learned yet.
Why D is correct
The problem is knowledge, not effort: the member cannot use a recently implemented system and the project is at risk of delay. The PM's job here is to close the knowledge gap in the fastest, least disruptive way, which means bringing in someone who already knows the system to support the member. That converts the individual's learning curve into a short handover instead of an open-ended self-study period.
Why the others are wrong
A. Asking the member to learn on the job is the slowest fix and does nothing to protect the threatened schedule.
B. A change request only moves the date; it does not solve the capability gap, and the PM should exhaust lower-cost fixes first.
C. Escalating performance to the sponsor treats a skill gap as a discipline problem and demotivates a willing employee.
PMP exam tip
Separate 'cannot do yet' from 'will not do'. Trainable skill gap plus schedule pressure = assign an experienced resource to support. Only consider escalation when the gap is behavioural.
3A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project.
What should the project manager do?
Reduce the number of approvers required to implement a change request
Request sponsor approval for all change requests to reduce the number of changes
Initiate the number of iterations to reduce the number of change requests
Add a fixed number of change requests allowed by the client on the project baseline
Answer: C
The short version
C — Increase the number of iterations to reduce the change requests. More, shorter cycles give the team and stakeholders frequent checkpoints at which new information can be absorbed as reprioritisation.
Key concepts in this question
Iteration: A fixed-length cycle that produces a usable increment; more iterations means more opportunities to inspect and adapt.
Incremental delivery: High uncertainty is the classic case for delivering in slices, because each slice generates learning that reshapes later slices.
Backlog reprioritisation vs. change requests: In agile, newly discovered work is normally ordered in the backlog rather than negotiated as a formal baseline change.
Predictive limits: A plan fixed upfront cannot absorb genuine uncertainty, which is why change-request volume explodes.
Why C is correct
The pain point is an excessive volume of change requests driven by uncertainty, so the corrective action must shorten the feedback loop rather than ration approvals. Adding iterations means stakeholders see and redirect work every cycle, so much of what would have been a change request becomes ordinary backlog refinement. The option's wording is clumsy, but the intent is the only lever among the choices that attacks the root cause.
Why the others are wrong
A. Fewer approvers weakens change control and still leaves the underlying inability to absorb uncertainty.
B. Routing all changes to the sponsor creates a bottleneck and formalises every discovery as an exception.
D. Capping the client's requested changes in the baseline sets a limit the customer never agreed to, converting a planning problem into a dispute.
PMP exam tip
Change-request flood from uncertainty? Add iterations and shorten the loop — never ration approvals.
4A project team is in the planning phase of a product migration project. The project manager schedules a meeting with the project team, telecommunications team, and the department leaders with group product accounts. The purpose of the meeting is to determine the project timeline based on how much content needs to be transferred to or created in the new system and the processing procedures and time frames.
Who should the project manager also invite to the meeting?
Representative from the provisioning team
Representative from the network team
Representative from the reimbursement team
Representative from the service desk team
Answer: A
The short version
A — Invite a representative from the provisioning team. Provisioning sets how fast products can be created or transferred in the new system, which is precisely what the meeting must size.
Key concepts in this question
Identify Stakeholders during planning: Estimation requires the input of the teams that actually perform the work; their volumes and processing times drive the schedule.
Provisioning: The function that creates, configures and activates products and services in the platform, so its processing time frames set the migration critical path.
Estimate activity: Estimates are more credible and faster when the people who do the work supply the rates and quantities.
Group product accounts: The accounts in scope determine the number of provisioning actions, which is why that stakeholder set is present.
Why A is correct
The stated purpose of the meeting is to determine the timeline from how much content must be transferred or created and how long processing takes. Only the provisioning team can supply both the per-unit volumes and the processing time frames, so including its representative makes the estimate defensible and surfaces dependencies early in planning. Vendor prose agrees, calling out provisioning as the group whose capacity and lead times govern the migration schedule.
Why the others are wrong
B. A network team has no authority over provisioning lead times or product creation in the target system.
C. Reimbursement operations act after products exist and so cannot inform migration duration.
D. A service desk handles post-launch support requests and contributes nothing to migration sequencing.
PMP exam tip
Estimating a migration? Invite the team that creates and activates the products — provisioning owns the real lead time.
5A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support at project completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.
What should the project manager do to resolve the conflict?
Seek to understand the project stakeholders’ needs in an effort to support the new technology.
Communicate the project’s progress to the stakeholders and promote the new technology.
Maintain and adhere to project plans to ensure the project delivers successful outcomes.
Acknowledge the lack of approval and focus on a resolution that will benefit the customer.
Answer: D
The short version
D — Acknowledge the missing approval and re-frame the resolution around customer value. The PM is not the technology's advocate; the missing approval and the support gap are the real problems to resolve.
Key concepts in this question
Approval authority: A technology the service organisation has not approved cannot be delivered; the sponsor's advocacy does not replace governance.
Servant leadership: The PM neutralises the sponsor's personal stake and reorients the discussion to the customer's outcome and long-term supportability.
Collaborative/problem-solving approach: Stakeholder conflict is addressed openly at the lowest level, escalating only to the authority that can approve.
Why D is correct
This is a conflict over an option whose benefits are promised rather than proven and whose operational support is conditional. The decisive move is to acknowledge the constraint openly — the technology is unapproved — and steer the resolution toward what benefits the customer, quantifying the support gap and putting the trade-off to the governance body with the authority to approve. Servant leadership means leading stakeholders to the right outcome, not championing the sponsor's solution.
Why the others are wrong
A. studying stakeholder needs to support the technology endorses the option before it is assessed
B. reporting progress and promoting the technology entrenches the sponsor and hides the unresolved approval gap
C. adhering to plans does not address an active conflict that puts operational support at completion at risk
PMP exam tip
Sponsor pushing an unapproved option: pick the answer that names the gap and puts customer benefit first — never the one that lobbies for the sponsor's technology.
6A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know how frequently the risks are being reviewed.
Which document project manager should check first?
Risk management plan
Risk register
Issue log
Risk report
Answer: A
The short version
A — Consult the risk management plan, which defines the frequency and timing of risk reviews. Once the cadence is confirmed, the risk register is where the PM reads the actual risk status.
Key concepts in this question
Risk management plan: Describes how risk management is performed: identification, qualitative and quantitative analysis, thresholds, and the frequency and timing of reviews.
Risk register: Holds the individual risks — description, owner, probability, impact, triggers and responses — but no cadence.
Issue log versus risk report: The issue log records events that have already occurred; a risk report is an optional periodic status summary, not the source of timing.
Why A is correct
The sponsor's question is about frequency of review, i.e. process attributes rather than risk data. The risk management plan states how risk identification, analysis, monitoring and audits will be performed and how often, so that is the first document to check. Once the cadence is known, the PM consults the register for the actual risk status.
Why the others are wrong
B. the register lists risks, owners and responses but does not state the review schedule
C. the issue log records problems that have already materialised, not future risk reviews
D. a risk report is a product of the process, not the place where review timing is defined
PMP exam tip
Sponsor asks "how often?" → plan. PM asks "what risks?" → register. Cadence is planned; content is recorded.
7A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested candidates, including former suppliers and suppliers recommended by the sponsor.
What should the project manager do in this situation?
Evaluate suppliers who have worked successfully with the company before
Request the contracting area take charge of the supplier evaluation process
Prioritize evaluation of the suppliers recommended by the sponsor
Evaluate the suppliers based on their experience and skills in similar projects
Answer: D
The short version
D — Evaluate suppliers on their experience and skills in similar projects. Procurement awards are decided by weighted, published criteria, not by familiarity or endorsement.
Key concepts in this question
Conduct Procurements: Bids are assessed against the weighted criteria set out in the procurement statement of work.
Objective decision-making: Fair, transparent scoring protects the process and produces an auditable recommendation.
Project manager accountability: The project manager owns the procurement process and the recommendation, even where contracting executes the paperwork.
Seller evaluation criteria: Typical criteria are experience, capability, cost, schedule risk and past performance with the organisation.
Why D is correct
Experience and skills on comparable projects is the standard, defensible criterion for predicting whether a seller can deliver this governance consulting work, and applying it uniformly to all bidders yields a traceable scoring outcome. That satisfies procurement control requirements and protects the project from the perception of bias. Vendor prose endorses D, stressing objectivity and project fit over familiarity or sponsor preference.
Why the others are wrong
A. Prioritising previous suppliers is incumbency bias and narrows the field without evidence of relevance.
B. Contracting can administer the tender, but the project manager still leads evaluation and the recommendation.
C. Weighting the sponsor's recommendations imports politics and undermines the objectivity of the award.
PMP exam tip
Supplier award? Weighted criteria, applied to everyone — never prior work with the company, never a sponsor favourite.
8A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability to perform a what-if analysis in the tool based on the customer demand and forecast.
What should the project manager do next?
Revise the project schedule and budget based on the additional scope, and review with the team.
Include the new capability to the product backlog and continue activities based on the current plan.
Perform an impact analysis on the schedule and budget based on the additional scope.
Analyze and negotiate with the executive steering committee regarding this new request.
Answer: C
The short version
C — Assess the schedule and budget impact of the new scope before anything is replanned or committed. Only once the impacts are quantified can the team and product owner re-order the backlog or accept a schedule change.
Key concepts in this question
Emergent and changing requirements: In an agile project the backlog is deliberately fluid, so a steering-committee request is a candidate item rather than an instruction to re-plan the sprint.
Impact analysis before commitment: Every scope addition is analysed for schedule, budget, quality and risk effects before it is accepted into a plan.
Governance versus delivery: Steering committees steer through priorities and constraints; the team, with the product owner, decides sprint content.
Why C is correct
The request arrives while sprint two is executing, so nothing can be committed to the current increment until the consequences are quantified. An impact analysis converts the steering committee's ask into stated schedule and budget effects, which is the input to any change decision and to re-ordering the release plan. It neither accepts the scope by rewriting the schedule nor ignores it.
Why the others are wrong
A. revising schedule and budget adopts the scope before its impact has been assessed
B. adding to the backlog presumes acceptance, leaves the impacts unassessed, and re-orders work the product owner owns
D. negotiating with the steering committee presumes the PM can overrule enterprise prioritisation instead of analysing impact first
PMP exam tip
Mid-sprint scope request → impact analysis first; plans and backlogs are updated only from that analysis.
9A company initiated a project to introduce a new product to the market. The product must undergo the industry’s regulatory process prior to approval and launch. However, the company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
Communicate with the industry’s regulatory authority to grant the company an exception.
Hire a third party who is an expert on the industry's regulations to work out the details.
Escalate the issue to the company’s CEO who has experience with the regulations.
Comply with the regulatory requirements and work to compress the project schedule.
Answer: D
The short version
D — Comply with the regulatory requirements and compress the schedule. The regulatory process is a fixed constraint, so the answer is to shorten duration, never to skip compliance.
Key concepts in this question
Constraint vs. risk: An industry regulator cannot be negotiated, negotiated away or mitigated; it defines the mandatory path to launch.
Schedule compression: Crashing adds resources at increased cost; fast tracking runs activities in parallel and raises risk. Both shorten duration without cutting scope.
Compliance and quality: Removing mandated steps creates legal, safety and reputational exposure that outweighs any launch-speed gain.
Value focus: The business case still expects the product; the deadline pressure is a schedule problem, not a scope problem.
Why D is correct
The regulator's approval process is a non-negotiable constraint on the project, so the project manager must keep it intact and find the remaining duration elsewhere. Compressing the schedule, through crashing or fast-tracking, is the sanctioned technique for meeting a date without reducing scope or dropping a required regulatory step. Vendor prose confirms this reading and highlights parallel processing and resource reallocation as the legitimate levers.
Why the others are wrong
A. Requesting an exception assumes discretion regulators rarely have and risks the company's standing.
B. A third-party expert can speed up preparation and interpretation but cannot substitute for the regulator's own approval.
C. The CEO's experience may help navigate, but no internal authority can waive an industry regulator.
PMP exam tip
External rule in the way? Never seek an exception — comply, then crash or fast-track to recover the time.
10Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
Shift those key members and assign them to another project.
Cancel the meeting series until the marketing team provides a solution.
Consult the project team and discuss the key team members’ availability.
Consult the resource management plan and escalate to the sponsor.
Answer: D
The short version
D — Consult the resource management plan and escalate to the sponsor. Staff are owned by another department, so the change must travel the plan's defined authorisation route.
Key concepts in this question
Resource management plan: Defines how resources are acquired, assigned, managed and released, and who authorises changes to them.
Authority boundary: The project manager directs the project team, not the marketing department's staff.
Change control for resources: Reassigning people owned elsewhere requires the functional or sponsor-level approval the plan designates.
Late-stage visibility: Near completion, resource shifts affect transition and acceptance, so the sponsor must see them early.
Why D is correct
The project manager has no authority to move marketing staff to or from the project unilaterally; the resource management plan states the process and the approving level for exactly that action, and the sponsor is the level that can negotiate with the owning department or approve alternative resources. Following the plan and escalating is both the compliant and the effective path. The vendor note on this item questions the escalation half, but the plan-defined authorisation route is precisely what the PM must use.
Why the others are wrong
A. Stealing another project's resources inverts normal practice and exceeds the PM's authority.
B. Cancelling the meeting series solves nothing and delays alignment with a key stakeholder group.
C. Consulting the team produces input but no decision, because the team does not own those people either.
PMP exam tip
People who belong to another department? Take the resource plan to the sponsor — never reassign them yourself.