10 free sample questions from a bank of 70, with the correct answers and explanations. No signup required — start practising right now.
1Once the project's WBS has been created what process may happen next?
Estimate activity resources
Define activities
Estimate activity durations
Sequence activities
Answer: B
2You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
It means the largest schedule variance you can have is five percent.
It is the earned value divided by the planned value for your project.
It is the expectation of management to be 95 on schedule at 95 percent of the project.
It means you will need to earn at least 95 cents per dollar invested in the project.
Answer: A
3You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?
One
Five
Four
Zero
Answer: D
4You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
Expert Judgment
Decomposition
Rolling Wave Planning
Templates
Answer: D
5You are the project manager of the NHG. The following figure represents your project network diagram. Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect
Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?
The critical path will now take 26 days.
The critical path will now take 17 days.
The critical path will now take 23 days.
The critical path will now take 20 days.
Answer: C
6You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date.
What is your schedule performance index for this project?
80
1.02
102
0.80
Answer: D
7Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Precedence Diagramming Method
Schedule network template
Dependency determination
Activity on the Node
Answer: A
8Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?
Scope baseline
Organizational process assets
WBS
Enterprise environmental factors
Answer: C
9You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.
Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.
Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.
Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an
Answer: B
10Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget.
What is the to-complete performance index for this project?