PK0-005: CompTIA Project+ — Free Practice Questions
10 free sample questions from a bank of 861, with the correct answers and explanations. No signup required — start practising right now.
1DRAG DROP
During a gate review meeting, the deliverable was rejected by the customer.
Review the dashboard.
Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
Part 2: Select the proper document(s) to be updated.
Answer:
2A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
Train users on the proper use of the system.
Escalate the issue to the CCB.
Hold sessions to understand user challenges.
Track system usage and report user activity.
Log the issue in the project risk register.
Create a memorandum of acceptable use.
Answer: C, E
3Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
Daily stand-up
Project momentum
Performance feedback
Meeting minutes
Answer: C
4Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Evaluating the project
Releasing the resources
Closing the contracts
Reconciling the budget
Answer: D
5During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
Ishikawa diagram
Scatter diagram
Pareto chart
Decision tree
Answer: C
6Which of the following BEST describes how an organization should coordinate management of multiple related projects?
Apply the SDLC process.
Establish a program.
Consult the CCB.
Use different frameworks.
Answer: B
7A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
Status report
Project plan
Change log
Meeting minutes
Answer: D
8A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
Synchronous
Informal
Asynchronous
Formal
Answer: A
9As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Update the work breakdown structure.
Review the backlog.
Seek baseline approval.
Establish the resource pool.
Answer: C
10A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
Trigger the contingency plan and communicate with the stakeholders.
Work with the functional managers to create a work-around.
Submit a change request to the change control board.
Transfer the risk by hiring a new vendor who was successful on a previous project.