1DRAG DROP - You are the production supervisor at a manufacturing company. You are in the process of configuring the production control module and its parameters. A company plans to use manufacturing execution. Bill of materials (BOM) item consumption must be generated when items are reported at the operation level. You need to configure the Manufacturing execution production order defaults form to allow for back flushing on operations. How should you set up Automatic BOM consumption? To answer, drag the appropriate setting to the correct targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point. Select and Place:
MB-320 question 1
    Answer:
    2HOTSPOT - A company manufactures high-end speaker systems. You have different configurations available for customers to customize features including finishes and speaker materials. You have a product configuration model with bill of material lines and conditions for each component. A customer can optionally add on protective covers, but only if a non-metal material is selected. If any other material is selected, the covers cannot be added. You add the following attributes: You need to create an expression-based constraint that will only allow Corner Protection if Metal is not selected. How should you complete the expression? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point. Hot Area:
    MB-320 question 2MB-320 question 2
      Answer:
      3DRAG DROP - A manufacturer uses route operations and job scheduling. You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available. You need to adjust the efficiency percentage for the conveyor line calendar. Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. Select and Place:
      MB-320 question 3
        Answer:
        4A company produces paints and assembles bicycle frames. You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times. Which two options can you use? Each correct answer presents part of solution. NOTE: Each correct selection is worth one point.
        • Enter a value in the queue time after field for the painting operation
        • Make a resource group for each size and color and assign that group to the operation
        • Enter a value in the transit time on the painting operation
        • Enter a value in the queue time before field for the assembly operation
        • Build capabilities for each resource related to color
        Answer: A, D
        5DRAG DROP - A company manufactures automobile engines. You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines. You need to translate production plans into Dynamics 365 Finance and Operations elements. Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. Select and Place:
        MB-320 question 5
          Answer:
          6You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar. A machine in the facility is defective and must be closed for repairs for the next two days. You need to configure the resource calendar to close the resource for production for the next two days. What should you do?
          • Navigate to the resource group. Change the calendar to closed on the resource group.
          • Navigate to the calendar used for production and close the next two days.
          • Navigate to the resource. Change the calendar to closed on the resource.
          • Navigate to the resource and select Calendar deviations. Set the calendar to closed for the next two days.
          Answer: D
          7A manufacturing company is implementing Dynamics 365 Supply Chain Management. The company uses a standard costing model to value inventory. During the setup of the system, all areas that impact the standard cost of the item must be configured correctly to calculate a complete standard cost by using routing, Bill of materials (BOM) and overhead burden. You need to verify that all areas of the system are correctly configured. Which object does NOT impact the standard cost of manufactured items?
          • item group
          • cost groups
          • cost categories
          • BOM formula
          Answer: D
          8DRAG DROP - A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs. The company has recently seen an increase in demand and purchases another resource. The company uses the same costs per resource. However, the new resource costs more to run. The company must be able to track cost contributions for the new resource. You need to create a cost category for the new resource. Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. NOTE: Each correct selection is worth one point. Select and Place:
          MB-320 question 8
            Answer:
            9DRAG DROP - You are the product design manager for a computer manufacturer. Your new laptop model is configurable. There are restrictions on which hardware components can be selected depending on the model. You create configuration groups for hardware and software. You need to create a new laptop item number and configurations. In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order. Select and Place:
            MB-320 question 9
              Answer:
              10A company is looking to use Dynamics 365 Supply Chain Management. The company is in the process of redesigning and retooling an existing manufacturing plant to group similar, cellular operations to improve efficiency and minimize wasted time between operations. They want to locate raw materials close to where they are needed without losing reorder visibility. You need to set up their environment. Which kind of production type should you implement?
              • Lean manufacturing
              • Process manufacturing
              • Discrete manufacturing
              • Manufacturing execution
              Answer: A