Certified in the Governance of Enterprise IT (CGEIT) — Free Practice Questions
10 free sample questions from a bank of 362, with the correct answers and explanations. No signup required — start practising right now.
1Which of the following should be the PRIMARY consideration for an enterprise when prioritizing IT projects?
Results of IT performance benchmarks against competitors
Impact on the business due to expected project outcomes
Technical capability of the enterprise to execute the projects
Process owner expectations based on operational benefits
Answer: B
The short version
B — Business impact from expected outcomes drives IT project priority. Governance prioritizes investments by value delivered to enterprise goals, not by technical ease or isolated benchmarks.
Key concepts in this question
IT governance prioritization: ranking proposed projects so limited funds and talent flow to the highest enterprise benefit first.
Business impact: revenue, cost, risk, compliance and strategic enablement effects that justify an investment over alternatives.
Competitor benchmarks: useful context on performance gaps but secondary to direct value for this enterprise.
Technical capability: a feasibility constraint shaping sequencing and risk, not the primary ranking criterion.
Process owner expectations: operational viewpoints that matter yet remain narrower than enterprise-wide outcome analysis.
Why B is correct
B is correct because CGEIT and COBIT principles place stakeholder value and business outcomes at the center of governance. The board and executive leadership fund projects that advance strategy and manage risk, even when execution is demanding. Impact on the business therefore outranks benchmarking, capability or single-process benefits as the primary consideration.
Why the others are wrong
A. Benchmarks against competitors inform positioning but do not measure value to this enterprise, so they cannot lead prioritization.
C. Technical capability affects whether and how a project can be delivered, it does not decide which outcome matters most.
D. Process owner expectations reflect one operational lens, narrower than enterprise business impact across stakeholders.
CGEIT exam tip
For CGEIT prioritization, always elevate enterprise business impact above technical, benchmark or single-owner views.
2A regulatory audit assessed an enterprise's main transactional application as noncompliant. In addition to fines and required corrections, an agreement was reached to implement a set of governance controls over IT. Accountability for these controls is BEST assigned to which of the following?
Internal audit director
CIO
The board of directors
Application users
Answer: A
The short version
A — The internal audit director owns accountability for agreed governance controls. After a noncompliance finding, independent assurance must verify that remediation controls are designed and operating effectively.
Key concepts in this question
Regulatory noncompliance: a transactional application failure triggering fines, corrections and a commitment to stronger IT governance controls.
Accountability for controls: clear ownership for confirming that promised controls are implemented and remain effective.
Internal audit director: the independent assurance leader reporting to the audit committee, separate from operations and IT delivery.
CIO and board roles: the CIO implements systems and controls while the board oversees governance, neither provides independent attestation.
Application users: operational stakeholders who follow controls but cannot objectively assure their enterprise effectiveness.
Why A is correct
A is correct because the settled key assigns accountability to the independent assurance function rather than to those who operate the controls. The internal audit director validates remediation, tests control design and operation, and reports directly to the board or audit committee. That independence is essential after an audit agreement involving fines and mandated governance improvements.
Why the others are wrong
B. The CIO owns delivery and operation of IT, so assigning assurance to the CIO would remove independence from the check.
C. The board retains ultimate oversight but delegates detailed control testing and follow-up to internal audit.
D. Application users execute transactions within controls, they do not own enterprise assurance over governance controls.
CGEIT exam tip
On CGEIT, link independence to audit: when controls follow a regulatory finding, accountability for assurance points to internal audit.
3A regional business unit of a major financial institution is considering the use of a Software as a Service (SaaS) cloud vendor to implement a new system. Which of the following should be performed FIRST?
Update the outsourcing policy.
Investigate on-premise software solutions.
Develop a business case.
Determine if the cloud vendor has a secure data center.
Answer: C
The short version
C — Develop a business case. Investment governance requires the business justification first; vendor security due diligence is a later, supplier-specific step that only matters once the SaaS option is actually being pursued.
Key concepts in this question
Business case as investment gate: COBIT requires a documented business case (with benefits, costs, risk and alternatives) as the basis for authorising an IT investment.
Outsourcing due diligence: supplier security, resilience and contractual review occur during evaluation of a chosen sourcing option, not before the need is justified.
Sequencing in investment decisions: strategy and business case, then option analysis, then supplier assessment and contracting.
Why C is correct
The financial institution's unit is considering a new system on a SaaS model. Governance discipline says you first establish why the investment is worth making and what alternatives exist, which is the business case. Only after that decision is framed do you examine the candidate vendor's controls, including whether it operates a secure data centre.
Why the others are wrong
A. The outsourcing policy is updated in response to a decision, so it cannot be the first step taken beforehand.
B. Investigating on-premise alternatives is analysis that belongs inside the business case, not a separate preliminary activity.
D. Confirming a vendor's secure data centre is due diligence on a chosen supplier; it presumes the decision to buy SaaS has already been justified.
CGEIT exam tip
On any FIRST-step question about a new technology or sourcing model, look for the business case; supplier checks always come later.
4During the implementation phase of a central ERP system, a project manager identifies a significant lack of human capabilities to support the system. The issue is reported to the project sponsor, and the sponsor sends a request for an increase in the budget to the IT steering committee. What should be the IT steering committee's FIRST action?
Require a revised business case.
Approve the budget request.
Provide appropriate training.
Refer back to the project sponsor for resolution.
Answer: A
The short version
A — Require a revised business case. The steering committee's authority is exercised against an approved business case, so a mid-project request for more money must first be re-justified before the committee can authorise it.
Key concepts in this question
Steering committee role: an IT steering committee directs and monitors IT investment; it is a governance body, not the delivery function.
Business case as the basis of authorisation: any change in scope, cost or resources requires the authorised business case to be updated and re-approved.
Resourcing gap during implementation: a skills shortfall is a change in project resourcing, which is a change to the authorised plan, not an emergency approval.
Why A is correct
The sponsor has identified a skills gap in a central ERP implementation and asked for more budget. Governance practice, and COBIT's investment management practice, require the project to remain within its approved business case; a funding increase changes benefits, cost, risk and schedule. The committee's first act is therefore to require a revised business case so the decision is evidence-based and auditable. It does not approve a request on the strength of a short verbal report.
Why the others are wrong
B. Approving the request skips justification entirely; the committee would be committing funds with no documented analysis or benefits baseline.
C. Supplying training is a management and PMO action; it is not a governance committee decision and presumes the answer before analysis.
D. Bouncing the request back to the sponsor achieves nothing; the committee's function is to require the proper artefact, not to delegate the problem.
CGEIT exam tip
Oversight bodies do not rubber-stamp requests; they demand the authorised artefact (business case) before deciding.
5For a large enterprise, which of the following is the BEST indicator that IT governance has a poor reputation?
Regulatory noncompliance
Low attendance at strategy committee meetings
High turnover of IT staff
Data leakage
Answer: A
The short version
A — Regulatory noncompliance best signals poor IT governance reputation. External failure to meet legal obligations damages trust more visibly than internal symptoms like turnover or meeting attendance.
Key concepts in this question
Governance reputation: stakeholder confidence that IT direction, risk and compliance are managed in the enterprise interest.
Regulatory noncompliance: public evidence that governance failed to ensure obligations, inviting fines and reputational harm.
Low strategy-committee attendance: a possible engagement warning but ambiguous and far less conclusive than legal breach.
High IT staff turnover: a human-capital concern that may stem from labor markets rather than governance failure.
Data leakage: a serious security incident that harms reputation yet is narrower than systemic governance noncompliance.
Why A is correct
A is correct because regulators, customers and boards judge governance by compliance outcomes. Noncompliance proves that policies, oversight and assurance did not prevent breach of duty, which directly undermines confidence in IT governance. As an enterprise-wide, externally visible indicator, it outweighs softer internal signals for the BEST reputation measure.
Why the others are wrong
B. Low attendance suggests weak engagement but could reflect scheduling or delegation rather than failed governance.
C. High turnover may indicate culture or compensation issues without proving governance itself is ineffective.
D. Data leakage is serious yet can occur despite reasonable governance, while noncompliance directly indicts governance oversight.
CGEIT exam tip
For CGEIT reputation questions, prefer the externally visible compliance failure over internal symptoms every time.
6An enterprise has committed to the implementation of a new IT governance model. The BEST way to begin this implementation is to:
prioritize how much and where to invest in IT.
identify the role of IT in supporting the business.
define policies for data, applications, and organization of infrastructure.
identify IT services that currently support the enterprise's capability.
Answer: B
The short version
B — Identify the role of IT in supporting the business. Governance policy, investment priorities and service definitions can only be built once IT's mandate and its link to enterprise strategy are explicit.
Key concepts in this question
IT governance model: COBIT and ISO/IEC 38500 frame governance as evaluate, direct and monitor; the foundation is a clear statement of IT's mandate and role.
Alignment before structure: governance decisions (how much to invest, what to standardise, which services to define) all follow from IT's agreed role in enabling the business.
Policy as an output, not a starting point: a policy is a governance instrument; it cannot be written before the role it governs is defined.
Why B is correct
Implementing a new IT governance model begins with determining and agreeing the role IT plays in supporting the enterprise, so that governance decisions are tied to business value and objectives. Every subsequent element in the answer set, investment prioritisation, policies for data, applications and infrastructure, and the current IT service inventory, is derived from that agreed role. Policy definition without a mandate is premature.
Why the others are wrong
A. Prioritising investment is a decision made inside the operating model, after the role and mandate are settled.
C. Defining policies is a core component of implementation but it presupposes the role of IT and the decision rights that support it.
D. Identifying current IT services is a state-of-the-art inventory step, useful for target design but not the starting point.
CGEIT exam tip
When a governance model is to be implemented, the first question is always: what is IT's role and mandate in this enterprise?
7Which of the following is the PRIMARY role of the CEO in IT governance?
Evaluating return on investment
Managing the risk governance process
Establishing enterprise strategic goals
Nominating IT steering committee membership
Answer: C
The short version
C — The CEO primarily establishes enterprise strategic goals for IT governance. Direction-setting from the top lets the board, CIO and risk owners align plans and investments afterward.
Key concepts in this question
CEO in governance: the chief executive articulates vision, strategic objectives and enterprise priorities that IT must enable.
Strategic goals: growth, market and efficiency aims that bound portfolio choices and define what good IT performance means.
Return on investment evaluation: detailed investment appraisal typically led by finance, CIO and portfolio owners, not the CEO alone.
Risk governance process: managed through risk committees and CRO or CIO structures under CEO-set direction.
Steering-committee membership: an organizing decision supporting governance, subordinate to setting enterprise direction.
Why C is correct
C is correct because frameworks assign the CEO primary responsibility for ensuring IT strategy derives from enterprise strategy. By establishing goals, the CEO creates the mandate against which IT value, risk and resource decisions are judged. Other roles then execute evaluation, risk management and committee design within that direction.
Why the others are wrong
A. Evaluating ROI is an appraisal activity owned by investment and IT leaders applying CEO-set goals, not the primary CEO act.
B. Managing the risk governance process belongs to risk and IT leadership operating the framework the CEO sponsors.
D. Nominating steering-committee members is administrative support for governance, not its primary executive purpose.
CGEIT exam tip
On CGEIT role questions, give the CEO direction-setting and give execution and assurance to CIO, risk and audit roles.
8Which of the following is a PRIMARY responsibility of the CIO when an enterprise plans to replace its enterprise resource applications?
Ensuring IT architecture requirements are considered
Selecting and vetting application vendors
Determining critical success factors for related projects
Establishing software quality criteria
Answer: A
The short version
A — The CIO ensures architecture requirements shape ERP replacement planning. Large application renewal must fit integration, data, infrastructure and standards constraints owned by the IT architecture function.
Key concepts in this question
ERP replacement: a landscape-level change affecting processes, data models, interfaces and hosting for the whole enterprise.
IT architecture requirements: principles, standards, target blueprints and integration patterns that protect coherence and reuse.
Vendor selection: commercial and functional sourcing work shared with procurement and business owners, supported by but not led primarily by architecture.
Critical success factors: business-owned outcomes defined with sponsors and program managers for benefits tracking.
Software quality criteria: detailed engineering checks owned by QA and delivery teams within architectural guardrails.
Why A is correct
A is correct because the CIO is the primary steward of enterprise architecture, and ERP decisions lock in long-term constraints. Ensuring architecture requirements are considered prevents siloed selection, duplicate platforms and unintegrable data models. That stewardship duty outranks vendor vetting or project-level success metrics as the CIO primary responsibility.
Why the others are wrong
B. Selecting and vetting vendors is a joint sourcing task with business and procurement, not the CIO architectural primary.
C. Determining critical success factors belongs mainly to sponsors and program leadership focused on benefits and change.
D. Establishing software quality criteria is a delivery-level responsibility executed under architecture, not the top CIO duty.
CGEIT exam tip
When CGEIT asks the CIO primary in major application change, choose architecture stewardship over vendor or project tasks.
9When establishing a methodology for business cases, it would be MOST beneficial for an enterprise to include procedures for:
addressing required changes outside the business case.
updating the business case throughout its life cycle.
identifying metrics post-implementation to measure project success.
entering the business case into the enterprise architecture.
Answer: D
The short version
D — A business-case methodology most benefits from enterprise-architecture entry. Recording each case in the architecture repository connects investment logic to capabilities, standards and roadmaps.
Key concepts in this question
Business-case methodology: the standard lifecycle for proposing, approving, tracking and reviewing investments.
Enterprise architecture entry: lodging the case, outcomes and capability impacts where planners can trace alignment and reuse.
Out-of-scope changes: important change-control handling but narrower than ensuring architectural traceability for all cases.
Lifecycle updates: keeping cases current through execution, valuable yet procedural without the architecture linkage benefit.
Post-implementation metrics: success measurement that depends on first anchoring the case to architectural context and baselines.
Why D is correct
D is correct because the settled key emphasizes governance integration over document maintenance alone. Entering the business case into the enterprise architecture makes benefits, costs and capability effects visible to portfolio and architecture boards. That linkage improves reuse, avoids duplication and sustains strategic alignment, which the methodology needs most.
Why the others are wrong
A. Addressing changes outside the case handles exceptions but does not strengthen enterprise-wide alignment like architecture entry.
B. Updating the case through its life cycle is good hygiene yet remains document-centric without architecture traceability.
C. Identifying post-implementation metrics aids evaluation but is most powerful once the case is anchored in architecture context.
CGEIT exam tip
For CGEIT methodology questions, favor the answer that ties the artifact to enterprise architecture and portfolio alignment.
10The PRIMARY focus of a committee tasked with evaluating an IT project portfolio should be to ensure:
a consistent estimation methodology is leveraged.
the enterprise strategy is updated.
consistent selection criteria are applied.
an industry standard capability maturity model is used.
Answer: D
The short version
D — A portfolio committee primarily ensures a standard maturity model is used. Consistent capability assessment lets governors compare projects fairly and direct improvement where it matters.
Key concepts in this question
IT project portfolio evaluation: governing the mix of investments for balance, value and risk rather than managing single projects.
Capability maturity model: an industry-standard scale for rating process maturity, enabling benchmarked and repeatable assessments.
Estimation methodology: useful for cost and schedule accuracy but narrower than portfolio-level governance focus.
Enterprise strategy updates: owned by executive leadership, informed by but not the primary work of a portfolio committee.
Selection criteria consistency: important for fairness, yet in this settled view subordinate to standardized maturity assurance.
Why D is correct
D is correct because the settled key makes comparable maturity the primary lens for portfolio evaluation. Using an industry-standard model gives the committee a neutral baseline for capability, risk and readiness across diverse proposals. That standardization supports credible prioritization and targeted capability uplift beyond any single estimation or selection technique.
Why the others are wrong
A. A consistent estimation methodology improves forecasts but does not provide the portfolio-wide maturity assurance required here.
B. Updating enterprise strategy is executive direction-setting, not the evaluation focus of the portfolio committee.
C. Consistent selection criteria aid fairness, yet the settled primary emphasizes standardized maturity assessment instead.
CGEIT exam tip
On CGEIT portfolio items, when maturity model appears as the settled lens, rank standardized assessment above estimation detail.