1Once the make-or-buy analysis is completed, which document defines the project delivery method?
  • Procurement statement of work (SOW)
  • Procurement strategy
  • Terms of reference
  • Change request
Answer: B

The short version

B — procurement strategy defines the project delivery method after make or buy. Once sourcing direction is set, strategy records how work will be delivered and contracted.

Key concepts in this question

  • Make or buy analysis: deciding whether to produce in house or procure externally based on capability, cost, and risk.
  • Procurement strategy: the document capturing delivery method, contract types, and procurement approach for the project.
  • Procurement statement of work: detailed description of procured scope for sellers, written after strategy sets direction.
  • Terms of reference: assignment description often for services, narrower than delivery method selection.
  • Change request: formal proposal to alter baselines, unrelated to initial delivery method definition.

Why B is correct

B is correct because completion of make or buy analysis feeds directly into the procurement strategy, which defines the project delivery method. The strategy translates the buy decision into contractual vehicles, phasing, and responsibilities that guide subsequent procurement documents. A statement of work details what to buy, terms of reference detail an assignment, and a change request modifies an approved baseline. Only the procurement strategy holds the delivery method decision per the settled key.

Why the others are wrong

  • A. Wrong because procurement statement of work describes scope to be procured, but does not define the overall delivery method.
  • C. Wrong because terms of reference scope a specific service assignment, not the project delivery approach.
  • D. Wrong because a change request alters existing plans, rather than defining delivery method after analysis.

CAPM exam tip

After make or buy, think strategy defines how: SOW defines what, strategy defines delivery method.

2What are the project management processes associated with project quality management?
  • Plan Quality Management, Manage Quality, and Control Quality
  • Plan Quality Management, Manage Quality, and Cost of Quality
  • Manage Quality, Customer Satisfaction, and Control Quality
  • Customer Satisfaction, Control Quality, and Continuous Improvement
Answer: A

The short version

A — Plan Quality Management, Manage Quality, and Control Quality form the quality trio. The three cover planning, execution assurance, and inspection control.

Key concepts in this question

  • Plan Quality Management: defining quality standards, objectives, and how compliance will be demonstrated.
  • Manage Quality: translating the plan into practice through audits and process improvement during execution.
  • Control Quality: inspecting deliverables against standards to verify correctness and approve or rework.
  • Cost of quality: a technique measuring prevention plus appraisal plus failure cost, not a process.
  • Customer satisfaction and continual improvement: goals and philosophies that quality processes pursue, not process names.

Why A is correct

A is correct because the project quality management knowledge area contains exactly Plan Quality Management, Manage Quality, and Control Quality in the PMBOK structure. Planning sets measurable criteria, Manage Quality assures the process is followed and improved, and Control Quality verifies outputs through measurement and inspection. Cost of quality is an analysis tool inside those processes, while satisfaction and improvement are outcomes. The settled trio therefore matches the standard process set.

Why the others are wrong

  • B. Wrong because cost of quality is a tool for analysis, not the third quality management process.
  • C. Wrong because customer satisfaction is an objective pursued by quality, not a named management process.
  • D. Wrong because continuous improvement and satisfaction describe aims, while the process set requires Manage Quality.

CAPM exam tip

Memorize Plan plus Manage plus Control as the quality three: cost, satisfaction, and improvement are not processes.

3Which set of competencies should a project manager have?
  • Leadership, strategic and business management, and technical project management
  • Expertise in the industry, leadership and business management, and bilingual skills
  • Technical project management, expertise in every rote, and PMP certification
  • Expertise in every detail on project activities, PMP certification, and leadership
Answer: A

The short version

A — leadership plus strategic business plus technical project management define the triangle. PMI talent triangle balances leading, business sense, and delivery craft.

Key concepts in this question

  • Leadership: motivating, coaching, and guiding teams and stakeholders toward project success.
  • Strategic and business management: understanding industry, market, and organizational goals to align decisions.
  • Technical project management: applying processes, tools, and domain knowledge to plan and deliver work.
  • Industry expertise alone: useful context, but not a substitute for the balanced triangle.
  • Certification and language: credentials and bilingual skill support credibility, but do not define competency sets.

Why A is correct

A is correct because PMI defines project manager competence through the talent triangle of leadership, strategic and business management, and technical project management. Leadership drives people, business management connects work to value, and technical skill ensures disciplined execution. Options centered on industry expertise, rote mastery, bilingual ability, or certification alone omit one or more triangle sides. The settled key therefore selects the balanced trio as the required competency set.

Why the others are wrong

  • B. Wrong because industry expertise and bilingual skill are helpful extras, not the PMI defined competency trio.
  • C. Wrong because rote expertise plus certification omits leadership and business management balance.
  • D. Wrong because activity detail plus certification plus leadership misses strategic business management as a pillar.

CAPM exam tip

Recall the talent triangle: leadership plus business plus technical, not certs or languages.

4Select two key benefits of the Control Procurements process. (Choose two.)
  • Enables the development of make-or-buy decisions
  • Ensures that contract performance meets the terms of the legal agreement
  • Guarantees that legal agreements influence vendor selection
  • Assures that legal agreements guide contract closings
  • Helps determine whether a certain type of contract should be used
Answer: B, D

The short version

BD — contract performance assurance plus agreement guided closing are the Control Procurements benefits. Monitoring delivery and closing per terms protect value.

Key concepts in this question

  • Control Procurements: monitoring seller performance, managing changes, and confirming contract compliance through delivery.
  • Contract performance: verifying work meets legal agreement terms, with corrective action when it drifts.
  • Contract closing guidance: ensuring legal agreements direct orderly closure, claims handling, and records.
  • Make or buy: an earlier Plan Procurement decision, not a benefit of controlling active procurements.
  • Contract type selection: also a planning choice about vehicles, not a control phase gain.

Why BD is correct

BD is correct because Control Procurements ensures contract performance meets the terms of the legal agreement through performance reviews, inspections, and claims administration, while also assuring that legal agreements guide contract closings with proper acceptance and documentation. Make or buy development and contract type choice belong to planning, and vendor selection influence belongs to conducting procurements. The settled pair isolates the two monitoring and closure benefits unique to the control process.

Why the others are wrong

  • A. Wrong because make or buy decisions are made during planning, not as a benefit of controlling procurements.
  • C. Wrong because influencing vendor selection occurs during source selection, not during performance control.
  • E. Wrong because determining contract type is a planning decision that precedes control and closure.

CAPM exam tip

Control Procurements equals perform to terms plus close per terms: planning owns make or buy and type.

5A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
  • The project manager should identify and deal with stakeholders only during the execution phase.
  • Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Answer: B

The short version

B — stakeholder satisfaction is identified early and managed as an objective. Early attention prevents late resistance and rework.

Key concepts in this question

  • Stakeholder identification: building the long list of potential parties at project start, then analyzing interest and influence.
  • Stakeholder satisfaction: meeting legitimate needs and expectations as a managed project objective from initiation.
  • Execution only engagement: delaying stakeholder work until delivery invites missed requirements and opposition.
  • Objectives versus secondary: project objectives and stakeholder needs are balanced, not ranked as primary versus afterthought.
  • Satisfaction versus scope: satisfaction guides priorities, but does not demote defined objectives to secondary status.

Why B is correct

B is correct because identifying stakeholder satisfaction immediately and managing it as a project objective reflects proactive stakeholder practice. Early identification allows analysis, prioritization, and engagement planning while scope and plans are still flexible. Waiting until execution, treating stakeholders as secondary, or flipping objectives to secondary all invite conflict and change cost. The settled key therefore elevates early satisfaction management alongside objectives.

Why the others are wrong

  • A. Wrong because limiting identification to execution misses the initiation window when influence is cheapest.
  • C. Wrong because treating stakeholders as secondary priority undermines support needed for objectives.
  • D. Wrong because making objectives secondary to satisfaction inverts disciplined scope and goal management.

CAPM exam tip

Start stakeholders at start and manage satisfaction as an objective, never as execution only or secondary.

6Which of the following set of elements is part of an effective communications management plan?
  • Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information
  • Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology
  • Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology
  • Glossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan
Answer: A

The short version

A — escalation plus owner plus glossary plus methods form the communications plan core. The settled set covers path, people, language, and channel.

Key concepts in this question

  • Escalation processes: defined thresholds and routes for raising issues when normal channels stall.
  • Responsibility for communication: named owner accountable for crafting and conveying each information type.
  • Glossary of terminology: shared definitions that prevent misunderstanding across functions and vendors.
  • Methods and technologies: chosen channels and tools matched to message urgency and audience access.
  • Inputs versus contents: charters, directories, org charts, and management plans inform the plan but are not its elements.

Why A is correct

A is correct because an effective communications management plan specifies escalation processes, the person responsible, a glossary of common terminology, and methods or technologies used to convey information. Together they answer how to raise concerns, who speaks, what words mean, and by which channel. Phone directories, charters, org charts, and overarching management plans are inputs or assets, not plan contents. The settled option is the only one composed purely of genuine plan elements.

Why the others are wrong

  • B. Wrong because phone directory and project charter are inputs or assets, not communications plan contents.
  • C. Wrong because organizational chart and project management plan are inputs, not elements of the communications plan.
  • D. Wrong because legislation constraints and management plans are considerations or inputs, not core plan components.

CAPM exam tip

Plan contents equal escalation plus owner plus glossary plus methods: charters and org charts are inputs.

7What are the inputs of the Estimate Costs process?
  • Project management plan, work performance data, enterprise environmental factors, and organizational process assets
  • Project management plan, project documents, enterprise environmental factors, and organizational process assets
  • Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
  • Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Answer: B

The short version

B — Plan plus documents plus EEFs plus OPAs are Estimate Costs inputs. That quartet supplies scope, detail, constraints, and assets for costing.

Key concepts in this question

  • Project management plan: brings cost management, scope, and schedule baselines that bound the estimate.
  • Project documents: include lessons, risk registers, and resource needs that shape quantities and assumptions.
  • Enterprise environmental factors: market rates, inflation, and commercial data that constrain realistic costs.
  • Organizational process assets: templates, historical data, and estimating policies reused across projects.
  • Work performance data versus baseline: execution telemetry and approved budgets belong to monitoring, not initial estimating.

Why B is correct

Estimate Costs builds forecasts from authorized direction plus supporting detail plus external conditions plus institutional memory. The PMBOK input list names management plan, project documents, EEFs, and OPAs as that combination. Vendor shorthand cites PMP plus docs plus OPAs plus EEFs for section 7 point 2. Options that swap in work performance data, cost baseline, or basis of estimates confuse downstream outputs or control inputs with the estimating start point.

Why the others are wrong

  • A. Work performance data measures execution and enters Control Costs, not the initial estimate.
  • C. Cost baseline is an output of Determine Budget, while benefits plan is not a listed estimating input.
  • D. Basis of estimates documents the result of estimating, so it cannot also be its own input.

CAPM exam tip

Estimate Costs inputs equal plan plus docs plus EEFs plus OPAs, outputs create basis, baseline comes later.

8Which is the order of steps in the Procurement Management process?
  • Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements.
  • Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements.
  • Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors.
  • Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements.
Answer: A

The short version

A — plan, solicit, negotiate, contract, then control is the procurement order. Logical flow moves from need to market to agreement to oversight.

Key concepts in this question

  • Planning procurement: identifying requirements and approach before engaging the market.
  • Obtaining quotes or proposals: soliciting seller responses once needs are clear.
  • Negotiating and contracting: reaching terms and committing with selected sellers in sequence.
  • Controlling procurements: monitoring performance after award through closure.
  • Sequence logic: solicitation must precede negotiation, and award must precede control.

Why A is correct

A is correct because the appropriate procurement sequence is identifying and planning requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements. Each step produces the input the next needs: requirements shape solicitation, responses enable negotiation, agreement enables award, and award enables performance control. Any order that negotiates before soliciting, controls before planning, or solicits before planning breaks that dependency chain.

Why the others are wrong

  • B. Wrong because negotiating before obtaining quotes inverts solicitation and bargaining order.
  • C. Wrong because controlling procurements first places oversight before needs are even defined.
  • D. Wrong because obtaining quotes before identifying requirements solicits the market with no defined need.

CAPM exam tip

Memorize plan plus get quotes plus negotiate plus contract plus control as the fixed procurement chain.

9Which is the appropriate tool to identify the possible correlation between two elements in a process?
  • Scatter diagram
  • Cause-and-effect diagram
  • Histogram
  • Control charts
Answer: A

The short version

A — scatter diagram reveals possible correlation between two elements. Plotted pairs expose relationship patterns at a glance.

Key concepts in this question

  • Scatter diagram: paired observations plotted on two axes to show correlation, clustering, or outliers.
  • Correlation insight: direction and strength of association guide further causal investigation.
  • Cause and effect diagram: fishbone structure brainstorming categories of potential causes, not correlation measurement.
  • Histogram: frequency distribution of one variable, showing shape and spread without pairing.
  • Control chart: time ordered performance with limits to detect special cause variation.

Why A is correct

A is correct because identifying possible correlation between two elements in a process is the purpose of a scatter diagram. By plotting one element against the other, teams see positive, negative, or no association and can target root cause work accordingly. Cause and effect organizes theories, histogram shows single variable distribution, and control charts monitor stability over time. Only the scatter diagram directly tests paired association.

Why the others are wrong

  • B. Wrong because cause and effect diagrams categorize possible causes, but do not plot paired correlation.
  • C. Wrong because histograms display distribution of one element, not association between two.
  • D. Wrong because control charts track stability over time against limits, not bivariate correlation.

CAPM exam tip

Two elements plus correlation equals scatter: fishbone for causes, histogram for distribution, control for stability.

10What process is included in Project Integration Management?
  • Monitor and Control Project Work
  • Control Scope
  • Control Schedule
  • Develop Team
Answer: A

The short version

A — Monitor and Control Project Work belongs to Integration Management. Integration coordinates unified direction and oversight of the whole.

Key concepts in this question

  • Project Integration Management: unifying planning, execution, and change control across knowledge areas.
  • Monitor and Control Project Work: tracking overall progress against objectives and initiating corrective action.
  • Control Scope: scope knowledge area process for managing scope baseline changes.
  • Control Schedule: schedule knowledge area process for managing timetable changes.
  • Develop Team: resource management process for building team capability, not integration oversight.

Why A is correct

A is correct because Monitor and Control Project Work is an Integration Management process that compares actual performance to the plan and triggers change control across areas. Control Scope and Control Schedule live in their respective areas, while Develop Team builds people capability. Integration alone owns the cross cutting monitor and control of total project work, matching the settled classification.

Why the others are wrong

  • B. Wrong because Control Scope manages scope baseline within scope management, not integration.
  • C. Wrong because Control Schedule manages timetable within schedule management, not integration.
  • D. Wrong because Develop Team improves team competence within resource management, not integration oversight.

CAPM exam tip

Integration monitor equals whole project: scope, schedule, and team controls belong to their own areas.